Lisbon’s Eastern Hospital project cost jumps to €899 million, opening pushed to 2029
📌 Key Highlights & Context
- Cost increased from €334.5 million to €898.9 million
- Loss of €100 million EU recovery funds due to delays
- Opening delayed to 2029 and payment schedule extended to 2054
The HLO project was classified as a priority in 2008 and the public‑private partnership (PPP) tender launched in 2017 with a base price of €334.5 million. The government’s latest decree authorises a maximum expenditure of €898.9 million (excluding VAT), which also covers roughly €25 million already spent over the past two years.
Construction delays caused the loss of €100 million earmarked from the EU Recovery and Resilience Plan (PRR). In April, the government appointed a commission to renegotiate the management contract, aiming to adjust the PPP’s financial model and ensure the project’s continuity. The statement noted that any additional costs relate only to work directly linked to procedural and administrative delays attributable to the public contracting authority.
The revised agreement fixes 1 December 2029 as the new commissioning date for a 875‑bed hospital covering 180,000 m² in Marvila. The payment schedule now runs until 2054, and indemnity provisions address extra costs caused by the cited delays. Residents of Marvila and the wider Lisbon area will eventually benefit from a modern, consolidated health facility, but the higher price tag and postponed opening increase pressure on public finances.